Hydrogen’s Dark Horse Is Turquoise

At the study’s own caseThe study

What you can move

21 of the model’s 123 values. The copper band is the range the evidence publishes; the dark line is the study’s own setting.

The report's own case: the verified February 2026 European input set, the carbon sold in full at the model's blended price, and a documented low-leakage pipeline supply route.

31
EUR per MWh
75
EUR per MWh
81
EUR per tonne CO2
90
EUR million
8%
fraction per year
91.5%
fraction of the year
700
EUR per tonne
100%
fraction of output
0.07%
fraction of throughput
12
kWh per kg H2
52.4
kWh per kg H2
6
EUR per kg H2
10
EUR per kg H2
40
kilotonnes per year
5
readiness level
2
kg CO2e per kg H2
1
multiple of design rate
11.7%
fraction per year
30%
fraction per year
55.4%
fraction per year
2030
calendar year
The claim under testHypothesis 4 of 5

If green arrives at its projected 2030 floor before a first plant is financed, the window is a knife edge rather than a cushion.

Binding margin · EUR per kg H2
0.37holds
holdsstrainedflips

The study’s claim still stands at these settings.

At the settings this claim was tested at, the model returns holds.

Undercuts grey · passesUndercuts green · passesClimate rail · passes
Levelised cost
2.44EUR per kg H2
against the study’s case
Levelised cost no carbon
5.24EUR per kg H2
against the study’s case
Margin against grey
0.37EUR per kg H2
against the study’s case
Margin against green
3.584EUR per kg H2
against the study’s case
Grey effective point
2.81EUR per kg H2
against the study’s case
Electricity saving fraction
77.1%fraction
of the whole · tick is the study
Total energy ratio against electrolysis
1.356ratio
against the study’s case
Binding leak ceiling
0.63%fraction of throughput
of the whole · tick is the study
Near zero pass GWP100
passesgate
gate met
Final investment decision gate pass
passesgate
gate met
Hypothesis
Hypothesis

159 derived quantities, evaluated in the order the model declares. The expression under each is the model’s own.